Some operations need to follow one another without an avoidable gap. A machine setup followed by production is a common example: the sequence needs to preserve both the prepared machine and the intended timing.
Task Connection in Just Plan It supports this continuity between operations in a linear predecessor-successor relationship. Alongside job-level buffer indicators, it helps planners coordinate connected work and assess delivery margin.
A normal predecessor-successor relationship establishes sequence. The successor follows its predecessor, but a gap may remain because of resource availability or other scheduling conditions.
Task Connection adds a stricter timing relationship. The scheduling engine places connected tasks without an intervening waiting period in available working time, while accounting for resource calendars.
This distinction matters when operations cross nights, weekends, or other nonworking periods. A calendar-aware connection does not necessarily mean uninterrupted processing in elapsed time.
Model set-up and production separately
A laser-cutting operation may require an operator for setup while allowing the production run to proceed without continuous operator attendance. Separate tasks can represent these different resource requirements.
The model also needs a constraint that keeps production on the machine that was set up. The task connection maintains timing continuity, while the machine constraint maintains resource continuity.
Using only one of these rules may not reflect the actual process. Planners should check both resource assignments and timing when reviewing the calculated schedule.
Connected tasks can also support processes where waiting between operations affects product quality. However, a strict maximum elapsed time requires validation beyond a calendar-aware connection alone.
If a material cannot wait overnight, for example, the team must confirm that the configuration enforces this requirement across nonworking periods. A schedule that excludes nonworking time from its waiting calculation may not meet a physical expiry constraint.
Task Connections can also be included through Excel upload and API integration. Teams should validate the required fields and resulting task relationships before applying imported data to a live schedule.
The Job View provides options for displaying delivery buffer information. Planners can use the default late-job display, show positive and negative buffer values for all jobs, or display Buffer Level values.
These options help teams review delivery margin across the workload, including jobs that are not yet scheduled late. Buffer and Buffer Level should be interpreted according to the application’s definitions, particularly when comparing jobs with different durations.
A representative test should include an unavailable resource, a priority change, and a task connection that crosses a nonworking period.
Reviewing these scenarios helps confirm that connected operations remain on the appropriate resources, follow the required sequence, and respect the process’s timing requirements. This gives planners a clearer basis for coordinating production and assessing delivery commitments.